Prepare Now For Monday's Latest Road Construction Project

 
Posted Friday, July 11th 2014 @ 1pm  by Chuck LaTour, WOOD Radio news team

Get ready for another road construction project.

Crews are repairing 10.5 miles of concrete pavement on I-96 from Thornapple River Drive to the Kent/Ionia county line.

MDOT's John Richard tells WOOD Radio the project is taking longer than expected and drivers were complaining about the long delays on the weekend-only project.  So, to expedite the project, single-lane closures will occur weekdays from 9am Monday to 5am Thursday and weekends from 9pm Friday to 5am Monday.

Weekday work is currently scheduled to be completed on the following days: July14-17, Aug. 11-14 & Aug. 18-21. Weekend work is currently scheduled to be completed on the following days: July 25-28, Aug. 1-4 and Aug. 15-18.

All work is weather dependent and subject to change